Open full test in the appQ1. The instrument used to measure horizontal and vertical distances in plane table....
- A. Plane alidade
- B. U-frame
- C. Clinometers
- D. Telescopic alidade
Q2. Elevation of bench mark plus back sight (BM+BS) is termed as....
- A. Bubble axis
- B. Line of collimation
- C. Line of axis
- D. Height of instrument
Q3. Size of Gravels is defined in mm as....
- A. 0.002-0.20
- B. 0.20-4.75
- C. 4.75 -7.62
- D. 76.2-102.2
Q4. Temperature for curing of concrete samples in laboratory is......
- A. 10°C
- B. 20°C
- C. 15°C
- D. 25°C
Q5. Strength of 40 Grade steel in psi....
- A. 20,000
- B. 60,000
- C. 40,000
- D. 30,000
Q6. The braking up of the surface layer of road through the cracking irregular shaped figure is termed as....
- A. Crazing
- B. Creep
- C. Rut
- D. Pot hole
Q7. Coming up the sub grade material in the shape of slurry from the joints or crack in the result of traffic movement on concrete road is termed as....
- A. Bleeding
- B. Mud pumping
- C. Squeezing
- D. Mud jacking
Q8. The ratio of actual area irrigated and culture able command area is called....
- A. Crop Ratio
- B. Duty
- C. Intensity of irrigation
- D. Capacity factor
Q9. A road sign indicating some speed limit is a type of road sign....
- A. Informatory
- B. warning
- C. Mandatory
- D. Regulatory
Q10. Mass transit transport is....
- A. Metro rail
- B. Train
- C. Metro bus
- D. All of these
Q11. To prepare concrete of 1:2:4 with 1 bag of cement, bujree will be required as....
- A. 7 cft
- B. 6 cft
- C. 4 cft
- D. 5 cft
Q12. An establishment engaged with specific project on its expanses....
- A. Work charged
- B. Permanent
- C. Temporary
- D. Regular
Q13. One-meter height of mercury will be equal to the column height of water......
- A. 13.6 m
- B. 10 m
- C. 1 m
- D. 3.6 m
Q14. Symbol used for enterprise project structure (EPS) in primavera....
- A. Any one
- B. Triangle
- C. Square
- D. Pyramid
Q15. C.P.M stand for....
- A. Critical path method
- B. Construction progress method
- C. Cash payment mode
- D. Construction plant module
Q16. Attendance and quantity of work done by daily labor is recorded in.....
- A. M.B
- B. Muster roll
- C. Running bill
- D. Final bill
Q17. Mass of one bag of cement is....
- A. 40 kg
- B. 50 kg
- C. 65 kg
- D. 60 kg
Q18. The distance of center of gravity (CG) from base of a triangle of height h.....
- A. h/3
- B. 2h/3
- C. h/2
- D. h/4
Q19. With the help of section modulus, maximum bending stress is found by this formula....
- A. f = E/Z
- B. f = Z/M
- C. f = M/E
- D. f = M/Z
Q20. Local authority in Pakistan....
- A. Cantt board
- B. K.D.A
- C. C.D.A
- D. All of these
Q21. The specification not included in departmental standard specification is called....
- A. General
- B. Detailed
- C. Standard
- D. Special
Q22. What is the principal constituent of brick earth......
- A. Alumina
- B. Magnesia
- C. Lime
- D. Silica
Q23. The minimum slope of a stair should not be less then......
- A. 25°
- B. 50°
- C. 40°
- D. 30°
Q24. Sound absorbing co-efficient of air is....
- A. 1.00
- B. 10.00
- C. 100
- D. 1000
Q25. In closed traverse the algebraic sum of departure is......
- A. 90°
- B. 180°
- C. 360°
- D. 0°