Open full test in the appQ1. A triplicate form used to issue some articles from store is called....
- A. bin card
- B. indent
- C. demand slip
- D. Stock register
Q2. The quantity of cement (in bags) will be required for 100 sft, flush pointing with cement mortar (1:3) ....
- A. 2 bags
- B. 1.53 bags
- C. 0.53 bags
- D. 2.53 bags
Q3. The distance of C.G from vertex of a triangle of height "h"......
- A. h/4
- B. h/2
- C. 2h/3
- D. h/3
Q4. Showing end speed of limit is such type of road sign....
- A. warning
- B. informatory
- C. Regulatory
- D. mandatory
Q5. Prepared surface at which sub base or base layer of road is provided is called....
- A. under layer
- B. gradient
- C. formation
- D. Sub grade
Q6. The workers who are paid out of funds available for a project are....
- A. work charged
- B. permanent
- C. temporary
- D. Regular
Q7. Wing wall of a culvert usually deflects at........degree.
- A. 60
- B. 90
- C. 45
- D. 30
Q8. A bridge in which position of deck is below the supporting parts is called........bridge.
- A. through
- B. low level
- C. Deck
- D. skew
Q9. Tender is invited for....
- A. contract
- B. Piece work
- C. work order
- D. all of these
Q10. Center of earthquake is termed as....
- A. focus center
- B. seismic
- C. epicenter
- D. Quack center
Q11. Paint with white lead base is suitable for painting of....
- A. Wood work
- B. iron work
- C. both a & b
- D. plaster
Q12. The main property of a liquid which controls its rate of flow....
- A. Surface tension
- B. specific gravity
- C. viscosity
- D. cohesion
Q13. An air pollution control equipment....
- A. inertial separator
- B. telemeter
- C. Oscilloscope
- D. all of these
Q14. A small chamber constructed at the street ends to get storm water is called....
- A. lamp hole
- B. regulator
- C. cleanout
- D. Inlet
Q15. To get dry volume, wet volume of cement for 0.40 water cement ratio, water required will be....
- A. 14-liter
- B. 28-liter
- C. 20-liter
- D. 35-liter
Q16. Heat transfer through......
- A. convection
- B. radiation
- C. Conduction
- D. all of these
Q17. A dredger similar to crawler shovels......
- A. Bucket
- B. grapple/rock
- C. dipper
- D. hydraulic
Q18. In water bound macadam roads, binding materials is......
- A. cement
- B. stone dust
- C. Sand
- D. none of these
Q19. Ratio of concrete used in foundation......
- A. 1:2:4
- B. 1:1.5:3
- C. 1:1:2
- D. 1:4:8
Q20. Minimum height of headroom......
- A. 2.5 m
- B. 2.0 m
- C. 3.5 m
- D. 3.0 m
Q21. Chizzy formula is used to calculate......
- A. volume
- B. velocity
- C. discharge
- D. Area
Q22. Quantity of solids in water measured in milligram per liter is also equivalent to......
- A. PPM
- B. TDS
- C. Threshold no.
- D. Reynolds no.
Q23. Quantity of dry mortar in 100 cft mortar is....
- A. 50
- B. 20
- C. 30
- D. 40
Q24. Vertical distance between dip and crown of a trap....
- A. Cistern
- B. seal trap
- C. floor trap
- D. pedestral
Q25. A time period for which a particle of water detains in settling tank is called....
- A. stop period
- B. detention period
- C. dew time
- D. Design period