Sub Engineer Civil – GDA Gujranwala - 2018 – Past Paper Solved MCQs
Solved MCQs from the PPSC paper “Sub Engineer Civil – GDA Gujranwala - 2018”. Full paper has 80 questions; the first 25 are shown here with correct answers. Open the app to take the complete timed test.
Open full test in the appQ1. Difference of back bearing and fore bearing of a line in WCB system......
- A. 180°
- B. 360°
- C. 90°
- D. 270°
Q2. The instrument used to measure horizontal and vertical distances in plane table......
- A. Plane alidade
- B. u-frame
- C. telescopic alidade
- D. clinometers
Q3. The first reading of staff at a point or bench mark is called......
- A. Back sight
- B. fore sight
- C. any one
- D. inter sight
Q4. Focusing is done to remove.....
- A. parallax
- B. Shade
- C. magnification
- D. all of these
Q5. Leveling operation always starts from a.....
- A. T.L
- B. C.P
- C. B.M
- D. datum line
Q6. Red color of brick depends upon......
- A. alumina
- B. Sand
- C. burning
- D. iron oxide
Q7. Gypsum is added to cement at the time of manufacturing for the purpose of....
- A. increase the weight
- B. increase the setting time
- C. Increase strength
- D. Decrease the setting time
Q8. Sand is suitable for concrete work......
- A. medium sand
- B. Fine sand
- C. graded sand
- D. coarse sand
Q9. To gain better strength such sand is considered suitable for preparing mortar......
- A. course
- B. Fine
- C. graded
- D. medium
Q10. Ratio between ultimate and safe bearing capacities of soil is termed as....
- A. Bearing ratio
- B. safe ratio
- C. factor of safety
- D. safe ultimate ratio
Q11. Water bearing strata....
- A. deep well
- B. lake
- C. Sea
- D. aquifer
Q12. The curve which is introduced at the point of change of gradient is called....
- A. transition curve
- B. compound curve
- C. Simple curve
- D. vertical curve
Q13. Curve of varying radius is called....
- A. vertical curve
- B. transition curve
- C. compound curve
- D. Simple curve
Q14. Small temporary wall or fixing board in front of walls for guidance during setting out for any structure is called....
- A. Sign board
- B. toe-wall
- C. dwarf wall
- D. profile
Q15. The transverse slope of the road is called....
- A. side slope
- B. super elevation
- C. camber
- D. Gradient
Q16. Volume of one bag of cement is....
- A. 3 cft
- B. 2.5 cft
- C. 1.25 cft
- D. 1.5 cft
Q17. Number of bricks taken in 100 cft brick work....
- A. 1350
- B. 1400
- C. 500
- D. 1000
Q18. The vertical members of the frame of door are called....
- A. posts
- B. sills
- C. styles
- D. Heads
Q19. The concrete roads are also called.....
- A. flexible road
- B. country road
- C. urban road
- D. Rigid road
Q20. Measuring unit of moment of inertia in MKS system....
- A. cm3
- B. cm4
- C. m4
- D. in4
Q21. MOI of a square is....
- A. D4/36
- B. D4/12
- C. D4/6
- D. D4/24
Q22. Negative bending moment shows....
- A. jogging
- B. Hogging
- C. sagging
- D. tearing
Q23. When shear force at a point of beam is zero, the B.M is....
- A. average
- B. Maximum
- C. zero
- D. minimum
Q24. The property of material by virtue of which it disappears the deformation after removal of external load....
- A. elasticity
- B. Plasticity
- C. toughness
- D. rigidity
Q25. Ratio of stress to strain with in elastic limit......
- A. young's modulus
- B. modulus of rigidity
- C. section modulus
- D. bulk modulus