Sub Engineer Civil – Clubbed Test - PID+PSC+SDA+GDA - 2024 – Past Paper Solved MCQs
Solved MCQs from the PPSC paper “Sub Engineer Civil – Clubbed Test - PID+PSC+SDA+GDA - 2024”. Full paper has 80 questions; the first 25 are shown here with correct answers. Open the app to take the complete timed test.
Open full test in the appQ1. Difference of upper and lower staff readings taken by tachometer is called....
- A. Constant
- B. Horizontal distance
- C. Staff intercept
- D. Vertical distance
Q2. Maximum height range per day for brick masonry with cement mortar is......
- A. 1.5 M
- B. 2 M
- C. 2.5 M
- D. 1 M
Q3. The roof which slopes in two directions....
- A. Mansard
- B. Gable
- C. Hipped
- D. Gambrel
Q4. The isometric view of circle looks like a.......
- A. Hyperbola
- B. Ellipse
- C. Circle
- D. Parabola
Q5. How much water is required for cooking and drinking...?
- A. 23 lpcd
- B. 13 lpcd
- C. 07 lpcd
- D. 27 lpcd
Q6. One gallon is equal to.......liters.
- A. 3.75
- B. 4.54
- C. 10
- D. 6.25
Q7. Detention period required for a particle of water in plain settling tank......
- A. 10-12 hours
- B. 8-10 hours
- C. 3-4 hours
- D. 4-8 hours
Q8. This is most commonly used coagulant....
- A. Ferrous sulphate
- B. Alum
- C. Soda ash
- D. Chlorinated copper
Q9. An additional pump is installed at the pumping station as....
- A. Stand by
- B. Emergency
- C. Firefighting
- D. Future
Q10. Chizzy’s formula to calculate velocity of flow in meter/sec is....
- A. C√mi
- B. m√ci
- C. Ac√mi
- D. √cmi
Q11. If discharge, Q=21 cft and Velocity, V=3 ft/sec then cross section area of sewer will be....
- A. 24 sft
- B. 07 sft
- C. 63 sft
- D. 18 sft
Q12. Thickness of expansion joints provided in hollow block masonry......
- A. 10-15 mm
- B. 2-5 mm
- C. 15-20 mm
- D. 5-10 mm
Q13. Supports to grip the planks of formwork......
- A. Welding
- B. Yoke
- C. Joist
- D. Props
Q14. The under surface of the flight of stair....
- A. Flight
- B. Waist
- C. Soffit
- D. Landing
Q15. Generally, riser is adopted in stairs....
- A. 12"
- B. 18"
- C. 06"
- D. 24"
Q16. Necessary data for preparing an estimate of a project is....
- A. Rates
- B. Specifications
- C. Drawings
- D. All of these
Q17. Details not shown in the drawing is presented by.......
- A. Specifications
- B. Drawings
- C. Rates
- D. BOQ
Q18. One mega Pascal=.......
- A. 1N/mm2
- B. 1Kn/cm2
- C. 1Kg/cm2
- D. 1N/m2
Q19. A bridge which is not at right angle to the direction of flow of water in plain is called....
- A. High level
- B. Low level
- C. Deck
- D. Skew
Q20. Capacity of a water tank should be such that, it should be able to meet at least........hour demand of the locality.
- A. 4
- B. 12
- C. 8
- D. 6
Q21. Number of bricks for 200 cft brick work is....
- A. 4050
- B. 1250
- C. 1350
- D. 2700
Q22. Well getting water from second or third water bearing strata....
- A. tube well
- B. artesian well
- C. deep well
- D. shallow well
Q23. CPM stands for......
- A. construction progress method
- B. cash payment mode
- C. critical path method
- D. construction plant module
Q24. Earth moving machine having swinging blade at its middle....
- A. Bulldozer
- B. Tractor
- C. Scraper
- D. Ripper
Q25. Method of monitoring a running project in primavera....
- A. Threshold
- B. Filter
- C. Sort
- D. Copy