Construction Project Planning and Management MCQs (Diploma Civil 3rd Year)
Free MCQs with answers for Construction Project Planning and Management. 125 questions in 11 chapter tests are in the app; a sample of 25 is shown here.
Open full test in the appQ1. This is an art of arranging various activities and group of peoples in an organization to achieve a common goal.
- A. Management
- B. Construction team
- C. Engineering
- D. All of these
Q2. A form of human association to achieve a common goal is called
- A. Organization
- B. Staff
- C. Project Team
- D. Construction team
Q3. To collect necessary data about the project ---- survey is carried out.
- A. Preliminary
- B. Detailed survey
- C. Interview
- D. All of these
Q4. Preparation of programme of construction orderly and systematically is called
- A. Execution
- B. Tendering
- C. Scheduling
- D. Planning
Q5. Construction machinery is used due to
- A. Economy
- B. Accuracy
- C. Fast speed
- D. All of these
Q6. A software used for project management in Civil Engineering.
- A. Primavera
- B. Eagle point
- C. Auto Desk
- D. Auto CAD
Q7. Carrying out constructional work according to specifications is called.......
- A. Progress
- B. Inspection
- C. Execution
- D. Quality control
Q8. In departmentally execution of work the enrolment of labour is carried out on......
- A. Running Bill
- B. Muster Roll
- C. M.B
- D. Pay Bill
Q9. The formal acceptance of the proposal by the administrative department is known as........
- A. Bid
- B. Technical sanction
- C. Grant
- D. Administrative approval
Q10. Detailed measurements in respect of works and supplies of materials are recorded in.
- A. M.B
- B. Final Bill
- C. Muster Roll
- D. Running Bill
Q11. Material and equipment of any division of works department is called.
- A. Store
- B. Depot
- C. Godown
- D. Deposit works
Q12. In project management this should be the main objective.
- A. Co-ordination
- B. Economy
- C. Progress
- D. Peace
Q13. The ratio between high management and middle level management senior staff of a good organization should be
- A. 1:3 to 1:5
- B. 1:7 to 1:10
- C. 1:5 to 1:7
- D. 1:1 to 1:3
Q14. Feasibility report is based on such estimate.
- A. Rough estimate
- B. Revised estimate
- C. Any one
- D. Detailed estimate
Q15. A schedule representing scheme of execution is called ---- schedule.
- A. Construction
- B. Finance
- C. Material
- D. Labour
Q16. Earth moving machine having blade at front.
- A. Scraper
- B. Ripper
- C. Tractor
- D. Bulldozer
Q17. The smallest unit in a project.
- A. activity
- B. enterprise
- C. node
- D. WBS
Q18. Quality control may be achieved by making,
- A. Execution
- B. Progress
- C. Inspection
- D. Quality control
Q19. Sanction of daily labour is accorded by
- A. XEN
- B. S.E
- C. S.D.O
- D. Chief Engineer
Q20. Approval sanctioned by competent authority for execution of construction project is termed as,
- A. Technical sanction
- B. Administrative approval
- C. Grant
- D. Bid
Q21. Measurement book may be required to produce in court of law as ........ in case of disputes.
- A. Record
- B. Evidence
- C. Pass book
- D. Charges
Q22. Over all control of stores lies with an officer called.
- A. XEN
- B. Sub-Engineer
- C. S.E
- D. SDO
Q23. Managerial function which decides what to do, when to do and how to do a job.
- A. Staffing
- B. Scheduling
- C. Planning
- D. Feed back
Q24. The ratio between middle level management and subordinates of a good organization should be
- A. 1:30 to 1:50
- B. 1:10 to 1:15
- C. 1:20 to 1:30
- D. 1:15 to 1:20
Q25. Project report is based on such estimate.
- A. Detailed estimate
- B. Any one
- C. Revised estimate
- D. Rough estimate
Chapters in this subject
Project Management, Organization, Preliminary Project Preparation, Construction Planning, Construction Machinery, Primavera (P6), Inspection and Quality Control, Methods of Executing Work and more.